safe and normal operation needs various concrete mixing plant departments’ clear division. Then the concrete mixing plant with which organization and which departments, various functional departments are responsible for the operation of concrete mixing plant which department?
1. Project Engineer: Responsible for overall factory direct management of production, technical, material equipment division three divisions.
2. Concrete mixing plant: responsible production department, with the technical, logistical General two departments. Subdivided into the production sector, the production team, responsible for the production. Transport sector is responsible for product transportation and transportation of raw materials feeding forklifts management. Equipment maintenance team, responsible for plant equipment repair and maintenance, daily water use of plant protection.
3. laboratory: the main responsible for the technical offer, with the concrete mixing plant stationmaster.
4. Substances Equipment Division: responsible for the supply of raw materials, product sales, logistics General three aspects of the work. Divided into the supply department, marketing department, administrative department three departments. Supply department, is responsible for procurement of raw materials, plant procurement. Marketing department, responsible for product sales, customer relationship, marketing. Administration Department is responsible for product security, plant safety and security. Logistics General, administrative implementation management.
阅读(104) | 评论(0) | 转发(0) |