2010-10-21 09:58:11

IBM CertificationIII 考试题库由我们专业IT认证讲师及产品专家精心打造,包括了当前最新的全真试题。题库的覆盖率在96%以上,确保考生能一次通过考试。

关于这门考试,考生需要了解以下的考试信息:

一、考试的时间及费用:

官方考试的费用是95美金,考试的时间为90分钟。

二、正式考试的题目以及及格的分数线:

56道的考试,及格分数是60分。

三、最新的考题的下载:

1. The functional requirements need a set of KPIs to support business activity monitoring. Which of the following components can be used to define KPIs?

A. Business Space

B. WebSphere Process Server

C. WebSphere Business Modeler

D. WebSphere Integration Developer

E. WebSphere Monitor Development Toolkit

F. WebSphere Service Registry and Repository

Answer: ACE

2. Non-functional requirements need a topology that supports high performance and throughput. What is the recommended method for Monitor to fulfill the requirements?

A. Queue Based

B. Queue Bypass

C. WS-Eventing

D. WS-Notification

Answer: B

3. A solution developer is testing a monitor model using the Unit Test Environment (UTE). While testing, the events are emitted synchronously from the event source. The events are accumulating in the system exception queue in the correct order and are not consumed by the monitor model.

What is the possible cause of this problem There is a problem in:

A. the Global Instance ID.

B. the Event Sequence Path.

C. evaluating the filter condition.

D. in evaluating the correlation condition.

Answer: A

4. A business analyst created a process model with associated KPIs in WebSphere Business Modeler and exported it to the Monitor Development Toolkit. The solution developer created another monitor model

with measures to support alerts based on instance measures for the same process.

Assuming both of the monitor models are valid, what is the best way for the solution developer to put the

KPIs and alerts definitions together in the same monitor model?

A. Combine the models with the Combine Monitor Models menu option, and choose to create a new monitor model.

B. Compare the models in a text editor, manually apply the changes from the business analyst and create a new monitor model by copying the XML.

C. Compare the models with the Compare With >Each Other menu option, accept each of the highlighted changes, and create a new monitor model by clicking Save a Copy.

D. Compare the models with the Compare With >Each Other menu option, accept each of the highlighted changes, and overwrite the previous monitor model by clicking Save as Right Contributor.

Answer: A

5. The solution developer installed Business Space within a deployment environment with a remote database, and has successfully completed the initial Business Space configuration from the WebSphere Application Server admin console. How would the solution developer proceed with the database configuration?

A. Grant permissions on the existing tables for the Business Space application.

B. Business Space does not require separate tables from the monitor database, so not additional setup is required.

C. The tables must be created manually on the database server before using Business Space.

D. The tables have already been created by checking Create tables checkbox during the Business Space configuration process.

Answer: C

6. Which of the following is a measure in the context of Business Activity Monitoring (BAM)?

A. The minimal latency of the network.

B. The average score of a credit check.

C. The number of currently logged on users.

D. The maximal response time of the database system.

Answer: B